Climate Change Data

Revival Gold Inc.

Climate Impact & Sustainability Data (2023)

Reporting Period: 2023

Environmental Metrics

Total Carbon Emissions:Not disclosed
Scope 1 Emissions:Not disclosed
Scope 2 Emissions:Not disclosed
Scope 3 Emissions:Not disclosed
Renewable Energy Share:Not disclosed
Total Energy Consumption:Not disclosed
Water Consumption:Not disclosed
Waste Generated:Not disclosed
Carbon Intensity:Not disclosed

ESG Focus Areas

  • Responsible Mine Development

Environmental Achievements

  • Developing mine and site infrastructure plans that avoid new stream and riparian area disturbances and crossing, and, to the maximum possible extent, staying within existing historical project disturbance areas
  • Developing reclamation and closure plans that adopt successful historical reclamation practices and improves-upon post-closure water management and treatment practices, including incorporating membrane cover systems into waste rock storage facility designs
  • Utilizing low carbon emissions grid hydro power

Social Achievements

  • Prioritizing hiring locally, building an internal team, and contracting with external consultants, contractors and suppliers, that are Lemhi County and Idaho-based, and when those resources are unavailable, looking to neighboring States to bolster the project team

Governance Achievements

  • Not disclosed

Climate Goals & Targets

Long-term Goals:
  • Not disclosed
Medium-term Goals:
  • A feasibility study should be completed on the heap leach restart project once supporting lab and field studies referenced above have been sufficiently advanced
  • A scoping level economic assessment should be completed for mining and processing sulphide material in a potential second phase mill operation
Short-term Goals:
  • Additional heap leach metallurgical test work to verify recoveries and reagent requirements at Beartrack and assess the potential for run-of-mine leach at Haidee
  • Additional hydrogeologic characterization to refine the current estimates on the site-wide water balance and pit lake modeling
  • Additional environmental geochemistry characterization to support operational waste management planning and closure design
  • The current environmental baseline study program should be maintained to prepare for permitting and NEPA review of the first phase heap leach restart project
  • The development of a Plan of Operations in support of permitting the heap leach restart project

Environmental Challenges

  • Risks associated with potential mine development include sensitivity to gold price and permit delays
  • The project considers refurbishing and reusing much of the existing recovery plant and infrastructure. There is a risk that the refurbishment costs would exceed budgeted estimates
  • The Beartrack site is serviced by an existing Idaho Power Co. 69 kV power transmission line with limited excess capacity and with power available on a first come, first served basis
  • To account for the long leach tail observed during historical Beartrack operations, the metallurgical recovery calculated from column leach testing was increased by 2.3% of contained gold (approximately 11,000 ounces of gold in total) for Beartrack oxide and transition ores. Although the data supports this assumption, there is a risk that this added recovery may not be realized or may be delayed relative to the economic model assumptions
Mitigation Strategies
  • Additional heap leach metallurgical test work to verify recoveries and reagent requirements at Beartrack and assess the potential for run-of-mine leach at Haidee
  • Additional hydrogeologic characterization to refine the current estimates on the site-wide water balance and pit lake modeling
  • Additional environmental geochemistry characterization to support operational waste management planning and closure design
  • The current environmental baseline study program should be maintained to prepare for permitting and NEPA review of the first phase heap leach restart project
  • The development of a Plan of Operations in support of permitting the heap leach restart project
  • A feasibility study should be completed on the heap leach restart project once supporting lab and field studies referenced above have been sufficiently advanced

Supply Chain Management

Supplier Audits: Not disclosed

Responsible Procurement
  • Prioritizing hiring locally, building an internal team, and contracting with external consultants, contractors and suppliers, that are Lemhi County and Idaho-based, and when those resources are unavailable, looking to neighboring States to bolster the project team

Climate-Related Risks & Opportunities

Physical Risks
  • Not disclosed
Transition Risks
  • Not disclosed
Opportunities
  • Not disclosed

Reporting Standards

Frameworks Used: NI 43-101

Certifications: Null

Third-party Assurance: Not disclosed

UN Sustainable Development Goals

  • Not disclosed

Not disclosed

Sustainable Products & Innovation

  • Not disclosed

Awards & Recognition

  • Not disclosed