Revival Gold Inc.
Climate Impact & Sustainability Data (2023)
Reporting Period: 2023
Environmental Metrics
Total Carbon Emissions:Not disclosed
Scope 1 Emissions:Not disclosed
Scope 2 Emissions:Not disclosed
Scope 3 Emissions:Not disclosed
Renewable Energy Share:Not disclosed
Total Energy Consumption:Not disclosed
Water Consumption:Not disclosed
Waste Generated:Not disclosed
Carbon Intensity:Not disclosed
ESG Focus Areas
- Responsible Mine Development
Environmental Achievements
- Developing mine and site infrastructure plans that avoid new stream and riparian area disturbances and crossing, and, to the maximum possible extent, staying within existing historical project disturbance areas
- Developing reclamation and closure plans that adopt successful historical reclamation practices and improves-upon post-closure water management and treatment practices, including incorporating membrane cover systems into waste rock storage facility designs
- Utilizing low carbon emissions grid hydro power
Social Achievements
- Prioritizing hiring locally, building an internal team, and contracting with external consultants, contractors and suppliers, that are Lemhi County and Idaho-based, and when those resources are unavailable, looking to neighboring States to bolster the project team
Governance Achievements
- Not disclosed
Climate Goals & Targets
Long-term Goals:
- Not disclosed
Medium-term Goals:
- A feasibility study should be completed on the heap leach restart project once supporting lab and field studies referenced above have been sufficiently advanced
- A scoping level economic assessment should be completed for mining and processing sulphide material in a potential second phase mill operation
Short-term Goals:
- Additional heap leach metallurgical test work to verify recoveries and reagent requirements at Beartrack and assess the potential for run-of-mine leach at Haidee
- Additional hydrogeologic characterization to refine the current estimates on the site-wide water balance and pit lake modeling
- Additional environmental geochemistry characterization to support operational waste management planning and closure design
- The current environmental baseline study program should be maintained to prepare for permitting and NEPA review of the first phase heap leach restart project
- The development of a Plan of Operations in support of permitting the heap leach restart project
Environmental Challenges
- Risks associated with potential mine development include sensitivity to gold price and permit delays
- The project considers refurbishing and reusing much of the existing recovery plant and infrastructure. There is a risk that the refurbishment costs would exceed budgeted estimates
- The Beartrack site is serviced by an existing Idaho Power Co. 69 kV power transmission line with limited excess capacity and with power available on a first come, first served basis
- To account for the long leach tail observed during historical Beartrack operations, the metallurgical recovery calculated from column leach testing was increased by 2.3% of contained gold (approximately 11,000 ounces of gold in total) for Beartrack oxide and transition ores. Although the data supports this assumption, there is a risk that this added recovery may not be realized or may be delayed relative to the economic model assumptions
Mitigation Strategies
- Additional heap leach metallurgical test work to verify recoveries and reagent requirements at Beartrack and assess the potential for run-of-mine leach at Haidee
- Additional hydrogeologic characterization to refine the current estimates on the site-wide water balance and pit lake modeling
- Additional environmental geochemistry characterization to support operational waste management planning and closure design
- The current environmental baseline study program should be maintained to prepare for permitting and NEPA review of the first phase heap leach restart project
- The development of a Plan of Operations in support of permitting the heap leach restart project
- A feasibility study should be completed on the heap leach restart project once supporting lab and field studies referenced above have been sufficiently advanced
Supply Chain Management
Supplier Audits: Not disclosed
Responsible Procurement
- Prioritizing hiring locally, building an internal team, and contracting with external consultants, contractors and suppliers, that are Lemhi County and Idaho-based, and when those resources are unavailable, looking to neighboring States to bolster the project team
Climate-Related Risks & Opportunities
Physical Risks
- Not disclosed
Transition Risks
- Not disclosed
Opportunities
- Not disclosed
Reporting Standards
Frameworks Used: NI 43-101
Certifications: Null
Third-party Assurance: Not disclosed
UN Sustainable Development Goals
- Not disclosed
Not disclosed
Sustainable Products & Innovation
- Not disclosed
Awards & Recognition
- Not disclosed