Aurcana Corporation
Climate Impact & Sustainability Data (2016, 2018)
Reporting Period: 2016
Environmental Metrics
Climate Goals & Targets
Environmental Challenges
- Lower silver prices resulted in the mine being put on care and maintenance in December 2013.
- The mill failed to reach design production rates and projected silver recovery in 2012-2013.
- Unreliable resource model for estimating mineralization extent, complexity, and location.
- Mill assembled partly from used equipment unsuitable for design parameters.
Mitigation Strategies
- New metallurgical test work and information on Shafter deposit, Presidio Mine operation, and recent Aurcana operation used to create a new mine model and refine the mill feed processing flowsheet.
- Proposed activities to advance the Shafter project include cavity survey of Presidio workings, plan to improve definition of remaining Presidio mineralization, mapping Presidio workings, drilling to test zones, re-examining historic drill-hole data, updating the database, re-examining historic information, developing an accurate survey of land holdings, metallurgical testing, equipment inspection, thickener evaluation, and completing a pre-feasibility or feasibility study.
Supply Chain Management
Climate-Related Risks & Opportunities
Reporting Standards
Frameworks Used: NI 43-101, CIM Standards
Reporting Period: 2018
Environmental Metrics
Total Carbon Emissions:Not disclosed
Scope 1 Emissions:Not disclosed
Scope 2 Emissions:Not disclosed
Scope 3 Emissions:Not disclosed
Renewable Energy Share:Not disclosed
Total Energy Consumption:Not disclosed
Water Consumption:Not disclosed
Waste Generated:Not disclosed
Carbon Intensity:Not disclosed
ESG Focus Areas
- Environmental
- Social
- Governance
Environmental Achievements
- Reclamation of tailings disposal area and mill bleed water pond, qualifying as exempt from hazardous designation pursuant to the Bevill Amendment.
Social Achievements
- Not disclosed
Governance Achievements
- Not disclosed
Climate Goals & Targets
Long-term Goals:
- Not disclosed
Medium-term Goals:
- Drill 16 holes to test the zone east of mine-grid 53,750.
- Update the database with historic channel-sample information and re-sample some locations to confirm historic results.
Short-term Goals:
- Rehabilitate existing workings and complete a cavity survey of the Presidio workings.
- Develop a plan to improve the definition of the remaining Presidio mineralization.
- Complete geotechnical investigations to establish design stope dimensions and a ground control management plan.
- Complete hydrogeological investigations to determine expected water inflow by mine area.
Environmental Challenges
- Lower silver prices resulted in the mine being put on care and maintenance in December 2013.
- Design silver production rates were not met during 2012-2013 operations.
- Unreliable resource model for estimating mineralization extent, complexity, and location.
- Mill assembled partly from used equipment not fully suitable for design parameters.
Mitigation Strategies
- Updated mine plan incorporating updated costs.
- Recommended work program to upgrade inferred resources, including rehabilitation of workings, cavity surveys, geotechnical and hydrogeological investigations, drilling, and data updates.
- Metallurgical testwork to optimize and confirm whole-ore leach recoveries.
Supply Chain Management
Supplier Audits: Not disclosed
Responsible Procurement
- Not disclosed
Climate-Related Risks & Opportunities
Physical Risks
- Not disclosed
Transition Risks
- Not disclosed
Opportunities
- Not disclosed
Reporting Standards
Frameworks Used: NI 43-101, CIM Standards
Certifications: Null
Third-party Assurance: Not disclosed
UN Sustainable Development Goals
- Not disclosed
Not disclosed
Sustainable Products & Innovation
- Not disclosed
Awards & Recognition
- Not disclosed