Climate Change Data

Companhia Paranaense de Energia - COPEL

Climate Impact & Sustainability Data (1993)

Reporting Period: 1993

Environmental Metrics

ESG Focus Areas

  • Environmental
  • Social
  • Governance

Environmental Achievements

  • Initiated the Segredo Hydroelectric Plant, incorporating environmental impact mitigation measures such as the creation of an experimental station for ichthyological studies and the resettlement of families affected by the reservoir.
  • Developed a plan to divert the Rio Jordão to increase the Segredo hydroelectric plant's production capacity by 10%.

Social Achievements

  • Successfully resettled 88 families affected by the Segredo hydroelectric plant reservoir, providing them with land, housing, community facilities, and support for agricultural production.
  • Honored four employees for their contributions to Copel's history in northern Paraná.

Governance Achievements

  • Revised the company's Code of Ethics to address conflicts of interest and the use of company resources.

Climate Goals & Targets

Long-term Goals:
  • Construct the Salto Caxias hydroelectric plant.
Medium-term Goals:
  • Implement the natural gas transmission and distribution system in Paraná.
Short-term Goals:
  • Complete the Segredo hydroelectric plant and Rio Jordão diversion project.

Environmental Challenges

  • Resettlement of families displaced by the Segredo hydroelectric plant reservoir.
  • Implementing the infrastructure for natural gas consumption in Paraná (requiring a US$112 million investment).
Mitigation Strategies
  • Developed the Segredo I resettlement project, providing land, housing, and community support to displaced families.
  • Planned a US$112.5 million investment to implement the natural gas transmission and distribution system in Paraná.

Supply Chain Management

Climate-Related Risks & Opportunities